Industries
Sector cash cycles, worked through with published dates
Most sector finance pages say a business “waits to be paid”. This one counts the days. Each case below takes a round example amount and runs it through a timetable somebody has actually published: the NHSBSA's 2026 pharmacy payment dates, the statutory payment rules for construction contracts with HMRC's CIS rules on top, and Amazon's stated payout frequency. None of the businesses is real. The dates are, and every amount can be checked by hand.
At a glance
Days from the end of the month to the money
Counted from the last day of the month the dispensing or the work was done. The pharmacy and construction rows use the worked examples below; the marketplace row is the published payout interval.
| Case | What arrives | When | Days |
|---|---|---|---|
| Pharmacy, July 2026 dispensing, submitted by 5 August | Advance, on the items declared | 11 Aug 2026 | 11 |
| Pharmacy, same month | Reconciled balance | 1 Oct 2026 | 62 |
| Subcontractor, July 2026 valuation, CIS at 20% | Net payment, 81.7% of the valuation | 24 Aug 2026 | 24 |
| Subcontractor, same valuation | CIS deduction, as a credit against the company's PAYE bill | 22 Sept 2026 at the earliest | 53 |
| Subcontractor, same valuation | Retention, in two halves | 30 Jun 2027 and 30 Jun 2028 in the example | 334 and 700 |
| Marketplace seller on Amazon's stated cycle | Available funds | Every two weeks | 0 to 14 after funds become available |
Sources for the dates: pharmacy from the NHSBSA 2026 payment timetable; the subcontractor's final date for payment from the Scheme for Construction Contracts, Part II; the CIS credit against the company's own PAYE bill, due on the 22nd for electronic payment, from GOV.UK's CIS subcontractor guide and Pay PAYE tax; the marketplace cycle from Amazon's seller guide. Day counts are our own arithmetic on the published dates. The retention dates depend entirely on the example completion date and defects period, which come from the contract, not from any rule.
Case 1: community pharmacy
July 2026 dispensing: an advance on 11 August, the balance on 1 October
A pharmacy in England dispenses NHS prescriptions all through July 2026. It submits its end of month declaration through the NHSBSA's Manage Your Service portal by 5 August 2026. Community Pharmacy England explains that the advance is "based on the items declared on the FP34C and the latest available Average Item Value (AIV) for that pharmacy, less the value of prescription charges declared", paid four working days after the submission deadline, with the final reconciliation on "the 1st working day of the month approximately two months after" submission (CPE: monthly payments).
Say the advance works out at £96,000 and the month, once every item has been priced, comes to £100,000. Those two amounts are ours, for illustration. The dates are the NHSBSA's.
| Date | What happens | Cash in | Days after 31 July |
|---|---|---|---|
| 1 to 31 July 2026 | Dispensing. Stock paid for on the wholesaler's terms, which the NHS timetable doesn't touch | None | - |
| 5 Aug 2026 | FP34C declaration submitted by the 5th | None | 5 |
| 11 Aug 2026 | Advance paid on items declared times average item value, less prescription charges | £96,000 | 11 |
| 1 Oct 2026 | July reconciled: advance recovered, priced total paid, so the net receipt is the difference | £4,000 | 62 |
Example amounts are illustrative. Dates from the NHSBSA 2026 payment timetable, read 24 September 2026. If the month had been priced below the advance, the reconciliation would take money back instead.
Two things follow. First, when the submission is on time and the advance is close to the priced total, as it is here, most of the month is paid inside a fortnight, so the real working capital question is how the wholesaler's terms line up against the advance date, not the headline "two months". Second, the reconciled difference is the part a lender tends to miss. It moves with the mix of items, and a month heavy with expensive medicines can leave a larger balance outstanding for 62 days.
Submitting late changes the first date, not the second. On the NHSBSA's late timetable, July 2026 dispensing submitted after the 5th but by 21 August 2026 is paid on 1 September 2026: the spreadsheet gives one pay date for "reconciled prescriptions including advances". That's 21 days later than the on-time advance. Miss the latest date and, the NHSBSA says, no advance is calculated.
Every 2026 dispensing month
The same arithmetic for each month on the 2026 timetable. The early advance lands 9 to 12 days after month end, and the reconciliation 58 to 63 days after it, with the spread coming from weekends, bank holidays and month lengths.
| Dispensing month | Submit by | Early advance | Late: submit by, paid | Reconciliation | Days to advance / reconciliation |
|---|---|---|---|---|---|
| December 2025 | 5 Jan 2026 | 12 Jan 2026 | 22 Jan 2026, 30 Jan 2026 | 27 Feb 2026 | 12 / 58 |
| January 2026 | 5 Feb 2026 | 11 Feb 2026 | 19 Feb 2026, 27 Feb 2026 | 1 Apr 2026 | 11 / 60 |
| February 2026 | 5 Mar 2026 | 11 Mar 2026 | 24 Mar 2026, 1 Apr 2026 | 1 May 2026 | 11 / 62 |
| March 2026 | 5 Apr 2026 | 10 Apr 2026 | 23 Apr 2026, 1 May 2026 | 1 Jun 2026 | 10 / 62 |
| April 2026 | 5 May 2026 | 12 May 2026 | 21 May 2026, 1 Jun 2026 | 1 Jul 2026 | 12 / 62 |
| May 2026 | 5 Jun 2026 | 11 Jun 2026 | 23 Jun 2026, 1 Jul 2026 | 31 Jul 2026 | 11 / 61 |
| June 2026 | 5 Jul 2026 | 9 Jul 2026 | 23 Jul 2026, 31 Jul 2026 | 1 Sept 2026 | 9 / 63 |
| July 2026 | 5 Aug 2026 | 11 Aug 2026 | 21 Aug 2026, 1 Sept 2026 | 1 Oct 2026 | 11 / 62 |
| August 2026 | 5 Sept 2026 | 10 Sept 2026 | 23 Sept 2026, 1 Oct 2026 | 30 Oct 2026 | 10 / 60 |
| September 2026 | 5 Oct 2026 | 9 Oct 2026 | 22 Oct 2026, 30 Oct 2026 | 1 Dec 2026 | 9 / 62 |
| October 2026 | 5 Nov 2026 | 11 Nov 2026 | 23 Nov 2026, 1 Dec 2026 | 31 Dec 2026 | 11 / 61 |
| November 2026 | 5 Dec 2026 | 10 Dec 2026 | 21 Dec 2026, 31 Dec 2026 | On the 2027 timetable | 10 / - |
Transcribed from the NHSBSA's two 2026 spreadsheets ("submit by 5th" and "submit after 5th"). The NHSBSA notes that where a bank holiday falls in the first five days of a month, submission must be secured by the 6th and the payment date moves with it. Days counted by us from the last day of the dispensing month. November 2026's reconciliation falls in January 2027, outside the published timetable.
More on how the sector gets misread by generalist lenders: community pharmacy.
Case 2: construction subcontractor
A £50,000 valuation: £40,850 on the day, the rest on three other clocks
A limited company subcontractor, registered for CIS and paid under deduction at 20%, works on a subcontract with monthly valuation periods and a 5% retention. The subcontract doesn't set its own due dates, so the statutory Scheme for Construction Contracts fills the gap. Under it, an interim payment becomes due on the later of seven days after the end of the relevant period and the making of a claim, and the final date for payment is 17 days after that (Scheme, Part II, paragraphs 4 and 8). July's work is valued at £50,000 excluding VAT, and 30% of it is materials the subcontractor bought itself. The amounts and the retention rate are our example; 5% is the figure the government's 2017 consultation called typical (GOV.UK: retention payments consultation).
| Date | What happens | Amount | Days after 31 July |
|---|---|---|---|
| 31 Jul 2026 | Valuation period ends and the claim is made | £50,000 gross | 0 |
| 7 Aug 2026 | Payment becomes due, 7 days after the period | - | 7 |
| 24 Aug 2026 | Final date for payment. Retention of £2,500 held back, CIS of £6,650 deducted from the £47,500 paid, after taking out materials | £40,850 received | 24 |
| 19 Sept 2026 | Contractor's payment and deduction statement due, 14 days after the tax month (6 August to 5 September) ends | - | 50 |
| 22 Sept 2026 | Contractor pays the deduction to HMRC. The subcontractor's own PAYE bill for the same tax month is due, and it can enter its year-to-date CIS deductions on its Employer Payment Summary and pay less | Up to £6,650 less to pay | 53 |
| 30 Jun 2027 (example) | First half of the retention at practical completion, CIS taken at the rate that applies on the day it's paid | £1,075 after £175 CIS | 334 |
| 30 Jun 2028 (example) | Second half, after a 12-month defects period | £1,075 after £175 CIS | 700 |
Payment dates from the Scheme; the tax month and deadlines from GOV.UK (deductions, paying HMRC by the 22nd, PAYE due dates). Materials treated as 30% of every payment, the same way our retention release estimator does. Retention releases still follow whatever payment period the contract sets, so the money can arrive after these dates. HMRC's CIS 340 guide says a retention release is treated like any other payment, at the subcontractor's status "at the date of payment and not when the work was actually done" (CIS 340, paragraph 6.13).
The same valuation at each CIS status
What arrives on 24 August 2026 depends on the status HMRC has given the subcontractor. The retention is the same in every column.
| CIS status | Deduction | Received on the day | Share of the £50,000 valuation |
|---|---|---|---|
| Gross payment status (0%) | £0 | £47,500 | 95% |
| Registered, net payment (20%) | £6,650 | £40,850 | 81.7% |
| Not registered or not verified (30%) | £9,975 | £37,525 | 75.1% |
Rates from GOV.UK: make deductions and pay subcontractors. The deduction is worked on £47,500 (the valuation less the retention) with 30% taken out as materials. Our arithmetic.
The CIS deduction isn't lost, but a limited company only gets it back by paying less PAYE. GOV.UK says to send the Full Payment Submission as usual and an Employer Payment Summary with the year-to-date CIS total, and HMRC "will take your CIS deductions off what you owe". A company whose PAYE bill for the month is smaller than £6,650 carries the rest forward, but only within the same tax year; anything left after 5 April 2027 has to be claimed as a refund (GOV.UK: pay tax and claim back deductions). A small subcontractor with few employees can therefore have CIS money tied up for months, not 53 days. A sole trader waits longer still: deductions are set against the Self Assessment bill for the tax year, and any tax still owing for 2026 to 2027 is due by 31 January 2028.
How each part is read by a lender, and what fits: construction retentions and CIS. To run your own contract's retention dates, use the retention release estimator.
Case 3: marketplace seller
A fortnightly payout, and what it holds at any one time
Amazon's UK guide for new sellers says that under Fulfilment by Amazon it "collects payment from the customer and pays you available funds every two weeks" (Amazon UK: beginner's guide). That interval is the whole published cycle; how long stock sat before it sold is the seller's own number.
At an example £1,000 a day of sales, spread evenly, a sale on the first day of the cycle waits 14 days and one on the last day waits almost none. Just before each payout about £14,000 of sales, less fees and refunds, is sitting with the platform; averaged across the fortnight it's about £7,000. The word "available" matters: funds held back for returns, disputes or a reserve aren't in that payout. How eBay and Shopify describe their holds, and why a payout isn't an invoice a funder can advance against, is on online businesses and marketplace sellers.
What the cases have in common
The cash leaves on one clock and returns on several
In each case the business pays out on ordinary terms (a wholesaler, wages and materials, a stock supplier) and gets paid on a timetable it didn't set and can't negotiate. The gaps are predictable to the day, which is why a revolving credit line sized for the cycle usually fits better than a loan, and why the monthly figures a lender should look at are the NHSBSA schedule of payments, the CIS statements and retention ledger, or the platform's settlement reports, rather than annual accounts.
What these cases can't tell you: the other side of your own cycle. Wholesaler terms, subcontract payment periods, completion dates and stock lead times vary by business, and they decide how long cash is really out. Put your own dates against the published ones before sizing any borrowing.
Sources
Pharmacy dates: NHSBSA pharmacy payment timetable, both 2026 spreadsheets, and Community Pharmacy England: monthly payments. Construction payment dates: Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule, Part II. CIS: deductions, paying HMRC, claiming back deductions, PAYE due dates and CIS 340, all on GOV.UK. Retention practice: GOV.UK retention payments consultation (2017). Marketplace payouts: Amazon UK beginner's guide. All read on 24 September 2026. The example amounts, the day counts and the CIS arithmetic are ours.
Talk it through
Need another perspective?
You may already know which facility you think fits. The more valuable question is whether it's actually the right structure for what's happening in the business. We'll review the situation before suggesting possible routes. It costs nothing to have that conversation.
Thank you. It's with our team now.
A person reads every enquiry and we'll come back to you with what we think the right next step is. No obligation at any point.
What happens next
- A person on our team reads it. No need to know which facility you want first.
- If we can help, we may introduce you to a provider and tell you who they are.
- No charge and no obligation at any point. You decide whether to go further.
Practical questions
Before you get in touch
How long does a community pharmacy wait for NHS payment?
On the NHSBSA's 2026 timetable, a pharmacy that submits by the 5th gets an advance 9 to 12 days after the end of the dispensing month and the reconciled balance 58 to 63 days after it. July 2026 dispensing, for example, gets its advance on 11 August 2026 and its reconciliation on 1 October 2026. The stock behind it is paid for on the wholesaler's own terms, which the NHS timetable doesn't set.
What happens to the advance if a pharmacy submits after the 5th?
It arrives later. The late timetable gives one pay date that covers the reconciled prescriptions and the advance. For July 2026 dispensing that's 1 September 2026, 21 days after the on-time advance, as long as the submission is in by 21 August 2026. The NHSBSA says a submission received after the latest date gets no advance at all.
How much of a £50,000 construction valuation does a subcontractor receive on the day?
In our example (5% retention, 30% materials, registered for CIS at 20%) the subcontractor receives £40,850, or 81.7% of the valuation. The £6,650 CIS deduction comes back later as a credit against tax, and the £2,500 retention is released in two halves at completion and after the defects period. With gross payment status the figure on the day would be £47,500.
When does a limited company get its CIS deductions back?
It doesn't get a payment. It sets the deductions against what it owes through its own payroll scheme, by entering the year-to-date total on its Employer Payment Summary, and pays the balance by the usual date, the 22nd for electronic payment. Anything its PAYE bill can't absorb carries forward within the tax year, and whatever is left after the tax year ends has to be claimed as a refund.
How long does it take?
It varies by facility, so there isn't one number that fits every case. Some drawdowns against an existing facility complete within a day or two; arranging something new from scratch usually takes longer. We'll give you a realistic timeline once we understand your situation.
What information do I need?
To start, just a description of what’s actually happening in the business. If it progresses, the provider will ask for the usual things: recent accounts, a sense of turnover and trading history, and details of the specific need.